A factory upgrade changes the demands on its electrical system. New machinery adds running and starting loads, while expanded production changes which processes need backup during an outage. Planning electrical contracting services alongside diesel generator backup helps plant teams address these changes before the new line is commissioned.
The starting point is the plant’s existing supply and distribution network: available capacity, which loads must keep running, and how equipment will restart after a power failure. These decisions guide generator selection, panel modifications, cabling and transfer controls.
Apollo Power Systems brings these works together through electrical installation, generator works, testing and commissioning for industrial facilities. For plant heads, maintenance managers and project engineers, the following steps explain how to plan the upgrade from the initial electrical review through to handover.
A new production line can increase both running demand and the load applied when motors start. The existing generator may still start normally during an outage but struggle when the expanded plant reconnects. Reviewing backup power early helps identify which equipment the generator must serve and the order in which it should restart.
Apollo Power Systems handled this wider electrical scope for Berger Paints’ plant expansion in Hindupur. The work covered power-sanction approvals and the supply, installation, testing, and commissioning of an HT yard with a transformer, 365 kVA diesel generators, and control panels. Distribution, power and control cabling, lighting, and earthing completed the installation. Bringing these elements into the expansion scope connected generator backup with the infrastructure supplying the plant.
Begin by identifying the operations that need power during a mains outage:
For each operation, record how long it can remain without power and what happens when it restarts. Production equipment may tolerate a controlled pause, while PLCs and data systems may need UPS support through the generator transfer interval. Fire and life-safety systems have separate backup requirements governed by the fire-protection design.
Once backup priorities are clear, compare the expanded plant’s demand with the existing electrical network. This review shows where capacity is available and where upgrades are needed to transformers, panels, cables, or protection.
Build the load schedule around how the plant operates. Equipment ratings provide the starting point; operating hours, simultaneous use, and starting methods show how much demand the system must handle. Include:
Use the load schedule to group equipment by its role during an outage. This helps define the generator-backed circuits, restart order, and any UPS support needed for sensitive controls.
| Load type | Examples | Backup approach |
|---|---|---|
| Critical | Process control, safety systems | Backup with transfer or UPS support suited to the required continuity |
| Essential | Main production lines, cooling | Generator supply with a planned restart sequence |
| Non-essential | Offices, spare equipment | Disconnected during an outage to reserve capacity for essential loads |
With the essential-load schedule in place, assess the existing generator’s available capacity, operating condition, and maintenance history. Include the controls and transfer equipment in the review, since keeping the generator may still require changes to how the new loads connect.
The assessment establishes which approach fits the expanded plant:
Pay particular attention to motor starts. A group of machines starting together can impose a much higher demand than their normal running load. Planning the restart sequence lets the engineering team assess this demand and the resulting voltage dip, along with the generator’s ability to accept the load.
The next step is to connect the selected backup capacity to the plant’s distribution system. Apollo Power Systems’ electrical contracting work covers generator installation, HT and LT panels, cable laying and terminations, and earthing. These physical connections allow a generator to supply the designated production loads.
The transfer arrangement determines how essential circuits move between mains and generator supply. Interlocks and protection prevent unintended backfeed, while the control sequence governs generator starting, load connection and return to mains. Systems designed for parallel operation also require synchronising controls and protection for that operating mode.
Review the distribution works together with the transfer arrangement:
A diesel generator takes time to start and accept load. PLCs, process controls and data systems that cannot tolerate this interval may need UPS support. Identify these circuits during design so that the generator and UPS serve their respective roles in the backup system.
In an operating factory, the installation programme needs to follow the production schedule. A clear scope links engineering decisions to equipment supply, site works, and the shutdowns needed to carry them out.
Record the party responsible for each part of the work:
Plan the work in stages around agreed production shutdowns. Prepare cable routes and equipment locations before the changeover, then schedule isolations, connections and commissioning within the available outage window. Where temporary power is part of the plan, include its capacity, connections, protection and operating responsibility in the installation scope.
Compare proposals against the same equipment list and scope of work. Relevant industrial projects show the contractor’s experience, while the quotation should make responsibilities, exclusions and handover requirements easy to identify.
| Factor | What to check |
|---|---|
| Project experience | Similar factory upgrades completed |
| Licences | Valid licences for your location |
| Exclusions | What the quote leaves out |
| Handover | Documents, training and warranty terms |
Commissioning should demonstrate how the upgraded plant behaves during a power failure and after mains power returns. Test the complete operating sequence alongside the individual electrical checks, and record the readings and results against the agreed acceptance criteria:
Complete the handover with test reports, updated as-built drawings and operating instructions. Brief the plant team on the transfer and restart sequence, emergency controls and maintenance responsibilities. Apollo Power Systems also provides generator annual maintenance contracts, preventive maintenance, diagnostics and repairs, connecting the completed installation with ongoing equipment support.
Apollo Power Systems has completed more than 100 electrical projects over the past five years. Its electrical contracting and generator services cover installation, testing, commissioning and ongoing maintenance. The company holds a Super Grade license in Karnataka, Class A licences in Andhra Pradesh and Telangana, and an ESA Grade licence in Tamil Nadu. To discuss a factory upgrade, share:
We handle the supply, installation, testing, and commissioning of LT and HT panels, transformers, cabling, earthing, and generator works. Apollo Power Systems’ team can discuss the distribution changes, generator backup, and installation schedule needed to support the expanded plant.
A factory upgrade changes the demands on its electrical system. New machinery adds running and starting loads, while expanded production changes which processes need backup during an outage. Planning electrical contracting services alongside diesel generator backup helps plant teams address these changes before the new line is commissioned.
The starting point is the plant’s existing supply and distribution network: available capacity, which loads must keep running, and how equipment will restart after a power failure. These decisions guide generator selection, panel modifications, cabling and transfer controls.
Apollo Power Systems brings these works together through electrical installation, generator works, testing and commissioning for industrial facilities. For plant heads, maintenance managers and project engineers, the following steps explain how to plan the upgrade from the initial electrical review through to handover.
A new production line can increase both running demand and the load applied when motors start. The existing generator may still start normally during an outage but struggle when the expanded plant reconnects. Reviewing backup power early helps identify which equipment the generator must serve and the order in which it should restart.
Apollo Power Systems handled this wider electrical scope for Berger Paints’ plant expansion in Hindupur. The work covered power-sanction approvals and the supply, installation, testing, and commissioning of an HT yard with a transformer, 365 kVA diesel generators, and control panels. Distribution, power and control cabling, lighting, and earthing completed the installation. Bringing these elements into the expansion scope connected generator backup with the infrastructure supplying the plant.
Begin by identifying the operations that need power during a mains outage:
For each operation, record how long it can remain without power and what happens when it restarts. Production equipment may tolerate a controlled pause, while PLCs and data systems may need UPS support through the generator transfer interval. Fire and life-safety systems have separate backup requirements governed by the fire-protection design.
Once backup priorities are clear, compare the expanded plant’s demand with the existing electrical network. This review shows where capacity is available and where upgrades are needed to transformers, panels, cables, or protection.
Build the load schedule around how the plant operates. Equipment ratings provide the starting point; operating hours, simultaneous use, and starting methods show how much demand the system must handle. Include:
Use the load schedule to group equipment by its role during an outage. This helps define the generator-backed circuits, restart order, and any UPS support needed for sensitive controls.
| Load type | Examples | Backup approach |
|---|---|---|
| Critical | Process control, safety systems | Backup with transfer or UPS support suited to the required continuity |
| Essential | Main production lines, cooling | Generator supply with a planned restart sequence |
| Non-essential | Offices, spare equipment | Disconnected during an outage to reserve capacity for essential loads |
With the essential-load schedule in place, assess the existing generator’s available capacity, operating condition, and maintenance history. Include the controls and transfer equipment in the review, since keeping the generator may still require changes to how the new loads connect.
The assessment establishes which approach fits the expanded plant:
Pay particular attention to motor starts. A group of machines starting together can impose a much higher demand than their normal running load. Planning the restart sequence lets the engineering team assess this demand and the resulting voltage dip, along with the generator’s ability to accept the load.
The next step is to connect the selected backup capacity to the plant’s distribution system. Apollo Power Systems’ electrical contracting work covers generator installation, HT and LT panels, cable laying and terminations, and earthing. These physical connections allow a generator to supply the designated production loads.
The transfer arrangement determines how essential circuits move between mains and generator supply. Interlocks and protection prevent unintended backfeed, while the control sequence governs generator starting, load connection and return to mains. Systems designed for parallel operation also require synchronising controls and protection for that operating mode.
Review the distribution works together with the transfer arrangement:
A diesel generator takes time to start and accept load. PLCs, process controls and data systems that cannot tolerate this interval may need UPS support. Identify these circuits during design so that the generator and UPS serve their respective roles in the backup system.
In an operating factory, the installation programme needs to follow the production schedule. A clear scope links engineering decisions to equipment supply, site works, and the shutdowns needed to carry them out.
Record the party responsible for each part of the work:
Plan the work in stages around agreed production shutdowns. Prepare cable routes and equipment locations before the changeover, then schedule isolations, connections and commissioning within the available outage window. Where temporary power is part of the plan, include its capacity, connections, protection and operating responsibility in the installation scope.
Compare proposals against the same equipment list and scope of work. Relevant industrial projects show the contractor’s experience, while the quotation should make responsibilities, exclusions and handover requirements easy to identify.
| Factor | What to check |
|---|---|
| Project experience | Similar factory upgrades completed |
| Licences | Valid licences for your location |
| Exclusions | What the quote leaves out |
| Handover | Documents, training and warranty terms |
Commissioning should demonstrate how the upgraded plant behaves during a power failure and after mains power returns. Test the complete operating sequence alongside the individual electrical checks, and record the readings and results against the agreed acceptance criteria:
Complete the handover with test reports, updated as-built drawings and operating instructions. Brief the plant team on the transfer and restart sequence, emergency controls and maintenance responsibilities. Apollo Power Systems also provides generator annual maintenance contracts, preventive maintenance, diagnostics and repairs, connecting the completed installation with ongoing equipment support.
Apollo Power Systems has completed more than 100 electrical projects over the past five years. Its electrical contracting and generator services cover installation, testing, commissioning and ongoing maintenance. The company holds a Super Grade license in Karnataka, Class A licences in Andhra Pradesh and Telangana, and an ESA Grade licence in Tamil Nadu. To discuss a factory upgrade, share:
We handle the supply, installation, testing, and commissioning of LT and HT panels, transformers, cabling, earthing, and generator works. Apollo Power Systems’ team can discuss the distribution changes, generator backup, and installation schedule needed to support the expanded plant.
Yes, where its available capacity, condition, and load acceptance suit the additional equipment. The review should include motor-starting demand and the sequence in which machines reconnect to generator power.
Start with the loads needed for safety, process continuity and controlled shutdown or restart. Their demand and required interruption time determine the backup arrangement and whether full-factory coverage is necessary.
It can. Adding generator-backed circuits may require panel modifications, transfer equipment, and revised protection settings. The extent of the work depends on the existing distribution arrangement and the new loads.
Motor starting can place a much higher demand on a generator than normal running. The motor type, starting method and number of simultaneous starts affect selection. Staged restarting and suitable motor controls can help manage that demand.
Work can be staged around production, with isolations, final connections and commissioning scheduled during agreed shutdowns. Temporary power can support selected operations when it is included in the installation plan.
A generator needs time to start and take load. Equipment that cannot tolerate that interval may need UPS support to maintain power during the transfer.
Provide the site location, existing electrical drawings, new machinery details, available load data, and shutdown constraints.