Overview:

Client: CIM Tools (Motherson Group)
Location: Bangalore
Scope: Backup Power Solution
System Size: 2640 kVA
Equipment: FMTU and Kohler

Project Details:

  • Supply, Installation, Testing, and Commissioning: Implemented 1×500 kVA, 1×320 kVA, and 2×910 kVA DG sets with associated works.

Achievements:

  • Comprehensive Design and Installation: Designed the DG yard layout and powerhouse, synchronized the DG sets, and managed the complete electrification of the plant for efficient backup power.