Overview:

Location: Bangalore

Scope of Work:

Apollo Power Systems was responsible for setting up the electrical infrastructure for Berger Paints’ plant expansion in Hindupur. The scope included:

  • Obtaining all necessary government approvals for power sanctioning.

  • Supplying, installing, testing, and commissioning the HT yard, which included a transformer, 365 kVA diesel generators, and control panels.

  • Setting up the complete distribution network along with power and control cabling.

  • Installing the light fixtures across the facility.

  • Establishing an effective earthing system to ensure safety and reliability.

Key Highlights:

  • Delivered a reliable and durable electrical infrastructure.

  • Completed the project on time and within the allocated budget.